#23294
Error when creating a milestone in filtered tree grid
Projects > Dates > Milestones
If you have set the filter for the column "Type" in the above mentioned view for a project structure to the value "MS", then select a WBS element and click on the button "New milestone...", the following error message appears:
"Node not child of its parent."
If you then reset the filter, a milestone without a name appears in the tree grid below the WBS element, and the button for opening the editing dialog is grayed out.
Test
No test.